O
Louisa County
← All issues
zoningHigh priorityopen

Electric transmission facilities and Valley Link

Louisa County

Summary

A Dominion/Transource/FirstEnergy joint venture proposes 765 kV transmission routes crossing much of Louisa, including near a future school site and the Town of Louisa. The commission formally opposed the routes and asked Valley Link to suspend efforts and the State Corporation Commission to deny the request.

At a glance

Total mentions
5
Last 30 days
0

Last discussed Jun 15, 2026.

Impact analysis

💰Financial impact

Routes near established businesses, residences, and growth areas could affect property values and county tax revenue.

✅Who benefits

Residents, the Town of Louisa, farmers, and school communities whose properties and viewsheds would be spared or buffered.

⚠️Who could be affected

Valley Link's route preferences; ratepayers may ultimately bear costs of rerouting or delays.

Mentions & discussions (5)

MeetingJun 15, 2026approved

Board of Supervisors Regular Meeting - Jun 15, 2026

The Board added a zoning requirement that electric transmission infrastructure like substations go through the County's conditional use permit process — another lever in the fight against the Valley Link transmission line.

MeetingJun 11, 2026

Planning Commission Meeting - Jun 11, 2026

Staff noted the Board of Supervisors approved a comprehensive plan amendment for electric transmission facilities in May, with a conditional use permit hearing set for July 6. Residents are watching closely given the Valley Link power-line controversy.

MeetingMay 14, 2026

Planning Commission Meeting - May 14, 2026

The plan amendment gives the State Corporation Commission local standards to consider when approving new transmission routes — favoring existing corridors, co-location, and avoiding homes, farms and historic resources.

MeetingMay 14, 2026

Planning Commission Worksession - May 14, 2026

Louisa is considering requiring CUPs for big power lines and substations (69 kV and up), with standards for routing, setbacks, screening, and road protection. It's a response to growing regional transmission proposals and would give the county a formal say in how projects like these affect farmland and rural areas.

MeetingMar 12, 2026

Planning Commission Meeting - Mar 12, 2026

A Dominion/Transource/FirstEnergy joint venture proposes 765 kV transmission routes crossing much of Louisa, including near a future school site and the Town of Louisa. The commission formally opposed the routes and asked Valley Link to suspend efforts and the State Corporation Commission to deny the request.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Louisa County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.