Data-center building permits — one cost $489,000 — produced a $1.1 million surplus that state law requires be spent on building-code functions. It could make the department self-sustaining during the construction boom, but it must eventually be spent on inspections and enforcement.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jan 5, 2026.
Impact analysis
$1,135,098.65 in restricted permit-fee revenue set aside for code enforcement and inspections.
General fund taxpayers, since the department may stop drawing on tax dollars for years.