Louisa County · issues
Civic issues
Topics getting the most attention in Louisa County public meetings, ranked by how frequently they come up.
Demolition and Removal of Louisa County Broadband Towers
The county is tearing down its unused broadband towers, but the ham radio group that backs emergency communications uses a repeater on one of them and needs a new home. Supervisors asked staff to press for repeater space on future cell towers.
James River Water Authority Project
The river intake is done — water is flowing — and the whole James River Water Authority project stays on track for October 2027. It's a long-planned water source for the county's future growth.
Well Failures During Drought
Chairman Adams clarified that water restrictions on the Zion Crossroads and Lake Anna well areas come from drought, not data centers, which will draw from Northeast Creek Reservoir. Supervisor Woodward added that residential customers always get priority over data centers.
Valley Link project schedule delay
Valley Link has pushed back its schedule for posting route updates and its SEC filing — a delay with no new timeline, leaving residents waiting on details about proposed transmission routes.
Verizon copper telephone phase-out
Verizon plans to wind down its old copper phone network after October 23, pending FCC approval. Copper phones work when the power is out — replacements may not — so the county is watching whether residents can still reach 911 in emergencies.
1998 Aquifer Study Under Review
An old 1998 county study of the aquifer has surfaced, and staff is reviewing it. Supervisor Jones suspects it relates to groundwater concerns around Spring Creek development in the western end of the county.
Columbia Gas Transmission Line Upgrades
Columbia Gas wants to upgrade an existing east-west pipeline crossing the county, including a county-owned parcel. Early info suggests most work stays within existing easements.
Ferncliff and New Bridge water/wastewater plant upgrades
$33 million in reserve funds will upgrade the Ferncliff water plant and New Bridge wastewater plant, which discharges near Lake Anna. LACA and neighbors opposed any capacity expansion; the county insists it's restoring the permitted 99,000 gallons/day, not expanding.
Water Infrastructure Costs and Financing Strategy
The county will spend cash instead of new debt on mandatory wastewater plant upgrades at Ferncliff and New Bridge — including an $11.5 million clarifier deferred since 2015 — saving about $3.8 million a year. Aging water lines serving Northeast Creek will likely cost over $20 million in coming years.
Water and road infrastructure strains from growth
Residents warned the aging Mineral water pipeline is failing and roads aren't ready for data-center truck traffic. The Water Authority budget now includes the failing Mineral-Louisa line.
Water Authority: Bowler's Mill Dam and wastewater treatment upgrades
The county is saving for its share of a high-hazard dam fix (hoping grants cover 65%) and a federally required ammonia-nitrogen upgrade at the regional wastewater plant, shared 50/50 with the Town of Louisa.
Broadband construction near Kentucky Springs Road nearly resolved
The railroad-crossing snags holding up broadband near Kentucky Springs Road appear resolved, with construction expected to be scheduled soon — good news for residents waiting on connectivity.